Goals for IUP South Campus VRML Project
Deadline Completed Benchmark Group Member(s)
March 17 X Implementation Plan review All
X HTML of Implementation Plan completed McCarty, Bier
X Report on elevation grid data Bier
X Draft of text on Greek Village Hixson
X Draft of HTML introductory page Bier
X Draft of text on South Campus in general and the President's residence Dix
X 2D Image map and framework of web pages for South Campus McCarty
X Collection of graphics files & VRML objects begun Hixson
X Collection of audio files begun McCarty
March 31 X Elevation grid DEM data/conversion research and contact person with Ron Wilson and Bob Marx Bier
X Simple models of buildings completed McCarty
X Begin interior of President's residence Hixson
X Investigate CAD to VRML conversion Dix
X HTML Web pages completed except for final graphics Dix, McCarty
X Graphics/audio/3D files continue to be gathered Dix, Hixson
April 14 Graphics/audio/3D libraries completed Hixson, McCarty
Elevation grid complete Bier
Additional details of buildings begun All
Landscaping details begun All
April 18  HTML Web pages completed Hixson, McCarty
Begin constructing VRML World info files McCarty, Bier
Special features completed: athletic fields, stadium Bier, Dix
Continue adding details to other buildings Hixson, McCarty
April 21 Begin pre-review: test web pages/VRML pages on various machines and browsers All members
April 25 Finish details of other buildings and landscaping All
Begin final review All
April 27 Finish final review All
Final changes made All
April 28/ 30 Project completed 
Project presented to class
All members
May 4/5 Project presented to public All members